Hamburg Avenue Improvement Project

The City’s Capital Improvement Plan includes improvements to Hamburg Avenue (from Lakeville Boulevard to 202nd Street/County Road 50) in 2019. Proposed improvements include roadway widening and reconstruction, construction of new concrete curb and gutter, installation of storm sewer and watermain, and construction of new sidewalks/trails.

Project Timeline


  • Phase 1: April 22-June 30, 2019 (205th Street to 400’ south of 202nd Street)
    Beginning April 22, Hamburg Avenue will be reduced to one lane and closed to through traffic between 205th Street and 202nd Street. Phase 1 improvements include installation of watermain, water services and storm sewer, and street construction, including paving the first lift of asphalt.
  • Phase 2: June 30-August 30, 2019 (Lakeville Boulevard to 205th Street)
    Phase 2 improvements will begin after paving the first lift of asphalt on Phase 1. Phase 2 improvements include reclaiming the existing asphalt and underlying aggregate and paving the first lift of asphalt. Hamburg Avenue will remain open to traffic; however, the roadway will remain gravel for periods of time. The final lift of asphalt and trail construction, between Lakeville Boulevard and 400’ south of 202nd Street is scheduled to be completed in August.

Project Newsletters


Read through this project's newsletters in our Archive Center.

Helpful Documents


Special Assessments

Special Assessment Deferment

The Lakeville City Council can defer the payment of any special assessment on homestead property owned by an individual who is at least 65 years old or is unemployed due to a total and permanent disability and meets the income requirements. For more information, download the documents below.



  1. Alex Jordan

    Assistant City Engineer